Road | Description of Road Work | Projected Start Date | Projected End Date | Status |
---|---|---|---|---|
50th Avenue | Pulverize Existing Pavement & Relaid, Add 3" Base Course, 3" New Pavement, and 2' Shouldering from County Hwy F to 90th Street | May 2023 | September 2023 | In Progress |
95th Street | Pulverize Existing Pavement & Relaid, Add 3" Base Course, 3" New Pavement, and 2' Shouldering from County Hwy N to 750' North of 65th Avenue | May 2023 | September 2023 | In Progress |
10th Avenue | Chip Seal from 20th Street to Termini | May 2023 | June 2023 | Completed |
19th Avenue | Chip Seal from 80th Street to Termini | May 2023 | June 2023 | Completed |
20th Street | Chip Seal from Hwy 12 to 10th Avenue | May 2023 | June 2023 | Completed |
25th Street | Chip Seal from 35th Avenue to 37th Avenue | May 2023 | June 2023 | Completed |
26th Street | Chip Seal from Frontage Road to 35th Avenue | May 2023 | June 2023 | Completed |
35th Avenue
37th Avenue |
Chip Seal from 25th Street to 26th Street
Chip Seal from 25th Street to 26th Street |
May 2023
May 2023 |
June 2023
June 2023 |
Completed
Completed |
50th Avenue | Chip Seal from County Hwy X to 90th Street | July 2023 | August 2023 | Open - Due to Culvert Replacement |
90th Street | Chip Seal from Hwy 29 Ramp to South Termini | May 2023 | June 2023 | Completed |
Hwy 29 Frontage Road South | Chip Seal from 20th Street to 40th Street | May 2023 | June 2023 | Completed |
80th Street | Chip Seal from County Hwy X to Termini | May 2023 | June 2023 | Completed |
12th Avenue | Crack Fill from 40th Street to 44th Street | June 2023 | August 2023 | Open |
14th Avenue | Crack Fill from 44th Street to Termini | June 2023 | August 2023 | Open |
20th Street | Crack Fill from County Hwy X to County Hwy M | June 2023 | August 2023 | Open |
30th Avenue | Crack Fill from 30th Street to 50th Street | June 2023 | August 2023 | Open |
34th Street | Crack Fill from 55th Avenue to 60th Avenue | June 2023 | August 2023 | Open |
40th Street | Crack Fill from 20th Avenue to Hwy 29 | June 2023 | August 2023 | Open |
44th Street | Crack Fill from 10th Avenue to 14th Avenue | June 2023 | August 2023 | Open |
50th Avenue | Crack Fill from County Hwy T to County Hwy X | June 2023 | August 2023 | Open |
50th Street | Crack Fill from 10th Avenue to 20th Avenue
Crack Fill from 45th Avenue to County Hwy N |
June 2023
June 2023 |
August 2023
August 2023 |
Open
Open |
55th Avenue | Crack Fill from County Hwy M to 34th Street | June 2023 | August 2023 | Open |
60th Avenue | Crack Fill from County Hwy M to 34th Street | June 2023 | August 2023 | Open |
65th Avenue | Crack Fill from 90th Street to 102nd Street | June 2023 | August 2023 | Open |
67th Avenue | Crack Fill from 72nd Street to Termini | June 2023 | August 2023 | Open |
72nd Street | Crack Fill from County Hwy N to Termini | June 2023 | August 2023 | Open |
80th Street | Crack Fill from County Hwy X to Termini | June 2023 | August 2023 | Open |
90th Street | Crack Fill from County Hwy X to 65th Avenue | June 2023 | August 2023 | Open |
95th Street | Crack Fill from 65th Avenue to 750' North | June 2023 | August 2023 | Open |