Road Description of Road Work Projected Start Date Projected End Date Status
30th Avenue Crack Seal from 40th Street to 50th Street Aug 2019 Sept 2019
40th Street Crack Seal from Hwy 29 South to County Line Road Aug 2019 Sept 2019
50th Street Crack Seal from 46th Avenue to 50th Avenue Aug 2019 Sept 2019
50th Avenue Crack Seal from County Hwy T to County Hwy F Aug 2019 Sept 2019
90th Street Crack Seal from County Hwy X to 50th Avenue Aug 2019 Sept 2019
12th Avenue Chip Seal Aug 2019 Sept 2019 Complete
14th Avenue Chip Seal Aug 2019 Sept 2019 Complete
20th Street Chip Seal Aug 2019 Sept 2019 Complete
33rd Avenue Chip Seal Aug 2019 Sept 2019
44th Street Chip Seal Aug 2019 Sept 2019 Complete
103rd Street Chip Seal Aug 2019 Sept 2019
106th Street Chip Seal Aug 2019 Sept 2019
50th Street 2nd Layer of Pavement Sept 2019 Oct 2019
30th Avenue Pulverize Existing Pavement & Relaid, Add 3" Base Course, 3" New Pavement, and 2' Shouldering from 30th Street to 40th Street June 2019 Oct 2019
67th Avenue Pulverize Existing Pavement & Relaid, Add 3" Base Course, 3" New Pavement, and 2' Shouldering June 2019 Oct 2019
72nd Street Pulverize Existing Pavement & Relaid, Add 3" Base Course, 3" New Pavement, and 2' Shouldering June 2019 Oct 2019

 

                    

Town of Wheaton 1st Grader originally on steel wheels that was converted to rubber wheels after Joe Hawkins purchased from the township.