Road Updates

Road Closures

Currently No Road Closures

Road Construction

Road Description of Road Work Projected Start Date Projected End Date Status
50th Avenue Pulverize Existing Pavement & Relaid, Add 3" Base Course, 3" New Pavement, and 2' Shouldering from County Hwy F to 90th Street May 2023 September 2023 In Progress
95th Street Pulverize Existing Pavement & Relaid, Add 3" Base Course, 3" New Pavement, and 2' Shouldering from County Hwy N to 750' North of 65th Avenue May 2023 September 2023 In Progress
10th Avenue Chip Seal from 20th Street to Termini May 2023 June 2023 Completed
19th Avenue Chip Seal from 80th Street to Termini May 2023 June 2023 Completed
20th Street Chip Seal from Hwy 12 to 10th Avenue May 2023 June 2023 Completed
25th Street Chip Seal from 35th Avenue to 37th Avenue May 2023 June 2023 Completed
26th Street Chip Seal from Frontage Road to 35th Avenue May 2023 June 2023 Completed
35th Avenue

37th Avenue

Chip Seal from 25th Street to 26th Street

Chip Seal from 25th Street to 26th Street

May 2023

May 2023

June 2023

June 2023

Completed

Completed

50th Avenue Chip Seal from County Hwy X to 90th Street July 2023 August 2023 Open - Due to Culvert Replacement
90th Street Chip Seal from Hwy 29 Ramp to South Termini May 2023 June 2023 Completed
Hwy 29 Frontage Road South Chip Seal from 20th Street to 40th Street May 2023 June 2023 Completed
80th Street Chip Seal from County Hwy X to Termini May 2023 June 2023 Completed
12th Avenue Crack Fill from 40th Street to 44th Street June 2023 August 2023 Open
14th Avenue Crack Fill from 44th Street to Termini June 2023 August 2023 Open
20th Street Crack Fill from County Hwy X to County Hwy M June 2023 August 2023 Open
30th Avenue Crack Fill from 30th Street to 50th Street June 2023 August 2023 Open
34th Street Crack Fill from 55th Avenue to 60th Avenue June 2023 August 2023 Open
40th Street Crack Fill from 20th Avenue to Hwy 29 June 2023 August 2023 Open
44th Street Crack Fill from 10th Avenue to 14th Avenue June 2023 August 2023 Open
50th Avenue Crack Fill from County Hwy T to County Hwy X June 2023 August 2023 Open
50th Street Crack Fill from 10th Avenue to 20th Avenue

Crack Fill from 45th Avenue to County Hwy N

June 2023

June 2023

August 2023

August 2023

Open

Open

55th Avenue Crack Fill from County Hwy M to 34th Street June 2023 August 2023 Open
60th Avenue Crack Fill from County Hwy M to 34th Street June 2023 August 2023 Open
65th Avenue Crack Fill from 90th Street to 102nd Street June 2023 August 2023 Open
67th Avenue Crack Fill from 72nd Street to Termini June 2023 August 2023 Open
72nd Street Crack Fill from County Hwy N to Termini June 2023 August 2023 Open
80th Street Crack Fill from County Hwy X to Termini June 2023 August 2023 Open
90th Street Crack Fill from County Hwy X to 65th Avenue June 2023 August 2023 Open
95th Street Crack Fill from 65th Avenue to 750' North June 2023 August 2023 Open

 

                    

Town of Wheaton very first grader originally on steel wheels that was converted to rubber wheels after Joe Hawkins purchased from the township.