Road Updates

Road Closures

Currently No Road Closures

Road Construction

Road Description of Road Work Projected Start Date Projected End Date Status
30th Avenue Pulverize Existing Pavement & Relaid, Add 3" Base Course, 3" New Pavement, and 2' Shouldering from 30th Street to 40th Street Jun 2019 Aug 2020 Completed
67th Avenue Pulverize Existing Pavement & Relaid, Add 3" Base Course, 3" New Pavement, and 2' Shouldering Jun 2019 Aug 2020 Completed
72nd Street Pulverize Existing Pavement & Relaid, Add 3" Base Course, 3" New Pavement, and 2' Shouldering Jun 2019 Aug 2020 Completed
50th Street Pulverize Existing Pavement & Relaid, Expand to 24' wide, Add 3" Base Course, 4" New Pavement, and 2' Shoulder from 10th Avenue to 20th Avenue.  Address Standing Water on Corner of 50th Street and 10th Avenue. Jul 2020 Oct 2020 Completed
55th Avenue Pulverize Existing Pavement & Relaid, Add 3" Base Course, 3" New Pavement, and 2' Shouldering from County M to 34th Street Jul 2020 Oct 2020 Completed
34th Street Pulverize Existing Pavement & Relaid, Add 3" Base Course, 3" New Pavement, and 2' Shouldering from 55th Avenue to 62nd Avenue Jul 2020 Oct 2020 Completed
60th Avenue Wedge and Overlay Pavement and 2' Shouldering from County M to 34th Street Sept 2020 Oct 2020 Completed
26th Street Chip Seal from County M to 25th Street and Service Road to South Aug 2020 Sept 2020 Completed
25th Street Chip Seal from 26th Street to Town Line Aug 2020 Sept 2020 Completed
65th Avenue Chip Seal from 25th Street to Termini and 124th Street to Hilary Avenue Aug 2020 Sept 2020 Completed
31st Avenue Chip Seal from 30th Street to 34th Street Aug 2020 Sept 2020 Completed
34th Street Chip Seal from 31st Avenue to 30th Avenue Aug 2020 Sept 2020 Completed
70th Street Chip Seal from 20th Avenue to 30th Avenue Aug 2020 Sept 2020 Completed
60th Avenue Chip Seal from 90th Street to Termini Aug 2020 Sept 2020 Completed
124th Street Chip Seal from County N to Mansfield Aug 2020 Sept 2020 Completed
66th Avenue North Chip Seal from 124th Street to Hilary Avenue Aug 2020 Sept 2020 Completed
90th Street Chip Seal from Termini to County X Aug 2020 Sept 2020 Completed
96th Street Chip Seal from County X to Termini Aug 2020 Sept 2020 Completed
80th Street Chip Seal from County F to Termini Aug 2020 Sept 2020 Completed
46th Avenue Chip Seal from 20th Street to Termini Aug 2020 Sept 2020 Completed
10th Street Chip Seal from 35th Avenue to Highway 29 Aug 2020 Sept 2020 Completed
50th Avenue Chip Seal from 10th Street to 20th Street Aug 2020 Sept 2020 Completed
10th Avenue Crack Fill from 50th Street to County T Aug 2020 Sept 2020 Completed
10th Street Crack Fill from 20th Avenue to 35th Avenue Aug 2020 Sept 2020 Completed
19th Avenue Crack Fill from 80th Street to Termini + Culdesac Aug 2020 Sept 2020 Completed
20th Avenue Crack Fill from County F to County T Aug 2020 Sept 2020 Completed
22nd Street Crack Fill from County M to Termini + Culdesac Aug 2020 Sept 2020 Completed
30th Avenue Crack Fill from 40th Street to 50th Street Aug 2020 Sept 2020 Completed
40th Street Crack Fill from 10th Avenue to Highway 29 and 60th Avenue to 65th Avenue Aug 2020 Sept 2020 Completed
50th Avenue Crack Fill from 20th Street to County M and County T to County F Aug 2020 Sept 2020 Completed
50th Street Crack Fill from 20th Avenue to Highway 29 and County X to 50th Avenue Aug 2020 Sept 2020 Completed
60th Avenue Crack Fill from County M to East 400 Feet and County T to Termini Aug 2020 Sept 2020 Completed
65th Avenue Crack Fill from 40th Street to 35th Street Aug 2020 Sept 2020 Completed
90th Street Crack Fill from County X to 50th Street and Highway 29 to Termini Aug 2020 Sept 2020 Completed

 

                    

Town of Wheaton very first grader originally on steel wheels that was converted to rubber wheels after Joe Hawkins purchased from the township.